Shift report
Reporting period 2026-10-16 07:00 - 15:00 · data cutoff 2026-10-16 11:00 SAST
Output against plan
Production stageCore Making (core sets)
Plan to now160 core sets
Accepted120 core sets
Rejected7 core sets
Variance-40 core sets
Attainment75%
Data coverageAll scheduled intervals to the demo clock reported
Breakdowns, downtime & maintenance
BKD-20261016-01 · Cold-Box Core Blower CB-01 (Blowhead Cylinder)
Repair Started
60 minTotal recorded downtime60 min
Material constraints & quality
Open material requests1
REQ-20261016-001: Phenolic Urethane Part A Core Binder Resin (Urgent batch top-up)
Acknowledged
Open quality flags1
QUAL-20261016-01: Core Softness & Gas Porosity Suspected
Under Investigation
Estimated exposure & assumptions
Estimated production value at riskR 6 000
RateR10 000/hr × 60% impact factor
Site hourly target (distinct)R 113 636
Illustrative assumptions — not a confirmed loss. Exposure stops accumulating after restoration.
Open actions, owners & due dates
Restore Core Blower CB-01 Blowhead & Verify Hydraulic Pressure
Owner: Johan Van Der Merwe · due 2026/10/16 · urgent
Expedite Catalyst Resin Supplier Delivery & Confirm ETA
Owner: Temba Sithole · due 2026/10/16 · high
Incidents (sanitised operational summary)
Open incidents1
INC-20261016-001: Core Shop · near miss · 16 Oct 2026, 08:40
Near Miss
routinePersonal names and medical detail are excluded from this summary; SHE-gated detail is on the incident page.
Handover commentary
Editable, saved with the report
Copyable text summary
Plain text — paste into email/WhatsApp
CAST PRODUCTS OIP — SHIFT REPORT Site: Cast Products / Pilot Foundry / Core Shop Period: 2026-10-16 07:00 - 15:00 SAST Data cutoff: 2026-10-16 11:00 SAST OUTPUT AGAINST PLAN (Core Making, core sets) Plan to now: 160 core sets Accepted: 120 core sets Rejected: 7 core sets Variance: -40 core sets Attainment: 75% Coverage: All scheduled intervals to cutoff reported BREAKDOWNS & DOWNTIME BKD-20261016-01 Cold-Box Core Blower CB-01 (Blowhead Cylinder) — repair started, 60 min, R 6 000 Total downtime: 60 min ESTIMATED EXPOSURE Estimated production value at risk: R 6 000 (illustrative) Site hourly target (distinct): R 113 636 MATERIAL CONSTRAINTS: 1 open REQ-20261016-001: Phenolic Urethane Part A Core Binder Resin (Urgent batch top-up) — acknowledged QUALITY FLAGS: 1 open QUAL-20261016-01: Core Softness & Gas Porosity Suspected — under investigation OPEN ACTIONS: 2 Restore Core Blower CB-01 Blowhead & Verify Hydraulic Pressure — owner Johan Van Der Merwe, due 2026/10/16 Expedite Catalyst Resin Supplier Delivery & Confirm ETA — owner Temba Sithole, due 2026/10/16 INCIDENTS (sanitised): 1 open INC-20261016-001: Core Shop — near miss, routine, follow up